Burnsville, Mississippi – Site Grading for Mississippi Silicon Corporation

This project consists of Site Development and Grading Operations for an upcoming steel production facility in which Mississippi Silicon Corporation, will be utilizing a submerged arc furnace to superheat raw materials to produce silicon metal in Burnsville, Ms. The project’s main scope of work includes approximately 40 acres of clearing and grubbing, 165,000 cubic yards of earthwork, and storm drain. Other aspects include contractor assistance for other trades as well as roadways and pad areas maintenance.

Oxford, Mississippi – Site Grading for Baptist Memorial Hospital

This $6.3 million project consisted of mass grading a 78 acre site for future construction of a new Baptist Memorial Hospital as well as constructing a four-lane roadway through the site connecting Old Taylor Road and Lamar Street, now known as Belk Boulevard. The diverse project consisted of clearing and grubbing the 78 acre site, approximately 800,000 CY of unclassified excavation, 4,200 LF of storm drainage system, curb & gutter and hot-mix asphalt. Other major items involved with the project were the placement of 19,000 Tons of crushed limestone base, demolition of an existing school structure, construction of a 900 CY triple-barrel box culvert, landscaping, electrical and erosion control.

Lowndes County, Mississippi – SeverCorr Steel Mill

This project was a 1400 acre site, involving 175 acres of clearing and grubbing, excavation of 4 million CY of 6′-12′ of expansive clay overburden that was stockpiled on-site and Demopolis chalk, that was ripped, broken down and stockpiled on-site. It also include the construction of a 36 acre and a 15 acre detention pond which included 645,000 CY of excavation. There was excavation and backfill of 53′ deep foundations for the new plant facility. Eutaw also constructed and graded 125,000 square yards of railroad, installed 5,000 linear feet of storm drain pipe structures.

Itawamba County, Mississippi – Toyota Boshoku Mississippi, LLC

Site construction including moving 348,000 CY of unclassified excavation, placement of 245,000 CY of select borrow material, 12,000 tons of chemical stabilization, and installation of approximately 3,700 linear feet of storm drain piping with 17 grate inlets. Project had a to be completed within 50 days, but was completed in less than 30 days.