S.R. 247 (DUPLEX ROAD) SPRING HILL, TENNESSEE

Eutaw Construction was awarded the $28.5 million S.R. 247 (Duplex Road) project in September 2017.  This project will serve as a major east-west arterial route through the City of Spring Hill between U.S Hwy. 31 (Main Street) and Interstate 65.  The project will provide sufficient access to developments, improve safety, and improve traffic operations. The City of Spring Hill partnered with Tennessee Department of Transportation (TDOT) to contract the widening of Duplex Road along an approximate 3.3-mile-long corridor with plans to provide one standard-width travel lane for each direction of travel and a center turn lane with sufficient shoulders.  As part of the planned road construction, above and underground utilities will also be relocated to make room for the new road and underground storm water infrastructure.

Houston, TX – Hurricane Harvey Relief


Eutaw loaded a trailer filled with supplies to aid the residents of Houston, TX and the surrounding areas.

Franklin, TN – Stephens Valley Subdivision

This project consists of water / sewer utility installation, off-site roadway improvements, and on-site mass excavation for a new subdivision on the south side of Nashville, Tennessee.  The first phase of this subdivision is approximately 40 acres, providing 88 lots, in what used to be farm land containing crops and livestock.

The overall scope of the project consists of the following: 8,140 linear feet of water main, 5,214 linear feet of gravity sewer, 65,000 cubic yards of mass grading, three (3) concrete box culverts with retaining walls, 5,120 linear feet of storm drainage, and 7,000 linear feet of electrical utilities.

DECATUR, AL – Beltline Road Sewer Extension

This project consists of furnishing and installing approximately 11,343 LF of 30” ductile iron force main along Hwy 20 in Decatur, AL.  Included in this pipe footage was 2,000 LF of pipeline that had to be installed by means of marine excavation through Decatur’s primary recreational & tourist attraction, Wheeler Lake.

Other areas of work for this project included the installation of 800 LF of 42” steel casing by jack & bore method and the installation of 5 air release vaults, valves and other misc. appurtenances.

This project was completed on time and under budget.