HINDS COUNTY, MISSISSIPPI – BYRAM CLINTON CORRIDOR

This Mississippi Office of State Aid Construction awarded the $19.5 million contract to Eutaw Construction.  The Byram – Clinton Corridor is a new construction project with 3.5 miles of 4-lane roadway and bridges in Clinton, Mississippi. The scope of work includes 100 acres of clearing & grubbing, 200,000 cubic yards of earthwork, 30,000 linear feet of storm drainage, 3 – double barrel concrete box culverts, 2 – concrete bridges, 69,000 linear feet of curb & gutter, 18,500 square yards of sidewalk,  68,000 tons of asphalt, water utilities, and traffic signals.