Picayune and Poplarville, Mississippi – Gulf Region Water/Wastewater Plan

The overall project consists of 4 separate smaller projects – W1, W2, S1, S2 – requiring the installation of approximately 250,000 LF of water and sewer force mains. Projects are located in Pearl River County, Mississippi and centered in the municipalities of Picayune and Poplarville. Dungan Engineering is the engineer for this project.

Orange Beach, Alabama – Orange Beach Water Authority

This project involved the installation of 14,325 LF of 30″ DIP/HDPE water main piping for Orange Beach Water Authority (OBWA). This piping connects water mains on Beach Boulevard to the piping on Canal Road increasing OBWA’s capacity for water service and fire protection. Other work performed was the installation of 500 LF of 36″ horizontal directional drilling under Shelby Lake and a 42″ steel encasement jack and bore under Canal Road.