Houston, TX – Hurricane Harvey Relief


Eutaw loaded a trailer filled with supplies to aid the residents of Houston, TX and the surrounding areas.

Franklin, TN – Stephens Valley Subdivision

This project consists of water / sewer utility installation, off-site roadway improvements, and on-site mass excavation for a new subdivision on the south side of Nashville, Tennessee.  The first phase of this subdivision is approximately 40 acres, providing 88 lots, in what used to be farm land containing crops and livestock.

The overall scope of the project consists of the following: 8,140 linear feet of water main, 5,214 linear feet of gravity sewer, 65,000 cubic yards of mass grading, three (3) concrete box culverts with retaining walls, 5,120 linear feet of storm drainage, and 7,000 linear feet of electrical utilities.

Hurricane Irma – Subcontract Registration Form

BUSINESS SIZE AND CLASSIFICATION

CHECK ALL THAT APPLY 

For assistance in determining your business size and classification, please CLICK HERE.

SERVICES PROVIDED

CHECK ALL THAT APPLY 

EQUIPMENT OWNED

(DO NOT INCLUDE ANY SUBCONTRACTED EQUIPMENT) 

Upload
Disclaimer: By providing the information requested to Eutaw, you promise that all information you provide will be accurate, current and truthful to the best of your knowledge. You further agree and acknowledge that Eutaw will be relying on the information, that Eutaw has no obligation to retain you as a subcontractor and that Eutaw reserves the sole and exclusive right to retain any subcontractor or no subcontractors at all for a particular project.
 
TO KNOWINGLY INPUT FALSE INFORMATION, INCLUDING, BUT NOT LIMITED TO NAME, PHONE NUMBER, ADDRESS AND COMPANY DATA IS A VERY SERIOUS AND FRAUDULENT MATTER THAT COULD RESULT IN SIGNIFICANT COSTS AND DAMAGES, AS WELL AS LOSS OF TIME, EFFORT
AND EXPENSE, AND ACCORDINGLY, IF YOU PROVIDE FALSE INFORMATION YOU WILL FULLY INDEMNIFY EUTAW AND BE LIABLE FOR ACTUAL DAMAGES, DIRECT, PUNITIVE AND CONSEQUENTIAL, AND ANY REGULATORY OR JUDICIAL FINES OR PENALTIES THAT MAY ARISE FROM SUCH MISLEADING, HARMFUL AND FRAUDULENT INFORMATION, PLUS REASONABLE LEGAL FEES, COST AND EXPENSES RELATING THERETO.

KNOXVILLE, TENNESSEE – PHASE 2 AIRFIELD MODERNIZATION PROGRAM (RUNWAY RECONSTRUCTION) AT MCGEE TYSON AIRPORT

In September 2016 Eutaw Construction was awarded a $22.3 million contract for Phase 2 of Knoxville’s Airfield Modernization Program at the McGee Tyson Airport.   The contract duration is 14 months.

The contract requires rehabilitation of the existing runway to meet the FAA’s line-of-sight requirements.  These requirements are designed to make it easier for pilots to see the entire runway during takeoff and landings.  The runway had a “crown” that needed lowering that limited the line-of-sight.  Approximately 3,500 feet of the runway required demolition and then replaced.

Definable features of the project include:

  • Removing and stockpiling of 210,000 square yards of portland cement concrete (PCC)
  • 80,000 square yards of asphalt removal
  • 10,000 linear feet of storm sewer removal
  • Site demolition
  • 1,126,000 cubic yards of unclassified excavation
  • 17,000 linear feet of reinforced concrete storm drain pipe varying in size from 18” – 60”, including the installation of 33 drainage structures
  • 640 linear feet of 5’ x 12’ concrete box culvert
  • 3,000 linear feet  of 10” ductile iron pipe water main
  • 2,300 linear feet of 6” sanitary sewer force main, including lift station relocation
  • 162,000 square feet of articulating concrete block system for erosion control
  • 6,000 LF of encased duct bank

Eutaw Construction also performed Phase 1 of the Airport Runway Modernization which included a similar scope.  The contract amount for Phase 1 was $24.6 million.