This project consists of water / sewer utility installation, off-site roadway improvements, and on-site mass excavation for a new subdivision on the south side of Nashville, Tennessee.  The first phase of this subdivision is approximately 40 acres, providing 88 lots, in what used to be farm land containing crops and livestock.

The overall scope of the project consists of the following: 8,140 linear feet of water main, 5,214 linear feet of gravity sewer, 65,000 cubic yards of mass grading, three (3) concrete box culverts with retaining walls, 5,120 linear feet of storm drainage, and 7,000 linear feet of electrical utilities.