Harahan, Louisiana – Harahan Pump to the Mississippi River

Eutaw teamed with Babcock Construction for the installation of a triple barrel run of 84″ steel pipe as part of a discharge system that runs directly beneath Hickory Avenue. Eutaw’s responsibility included all field supervision – specifically covering the design, installation, excavation and backfill of the 700′ long temporary retaining structure (TRS). The TRS required a 1,560′ wall of sheet piles driven to 55′ deep.